Tariffs In Construction: The Roller Coaster
What to consider as contractors navigate a tariff environment?
The last month and a half of the news cycle has been completely consumed with discussion of tariffs and their potential impact to the Canadian economy. What has made this situation even more difficult for businesses (including construction) is that goal posts and where potential tariffs will land is a significantly moving target. At FCA, we’ve gathered insights from owners, general contractors, subcontractors, accountants, and lawyers to highlight key areas contractors should focus on as they navigate this evolving landscape.
EXISTING CONTRACTS:
Contractual Language:
If projects are impacted by tariffs, contractors need to review their existing contracts and determine if there are avenues for cost recovery. If uncertain, contractors should be engaging strong construction lawyers and having them assist in these reviews. They should be looking at clauses like “change in law”, “force majeure” and any price escalation clauses as potential avenues for recovery. Change in law clauses can sometimes allow parties to offset a loss/damage faced by a party in the event of an alternation in law, of which one could argue a tariff would be included. Force majeure is a clause that provides a safety net when extraordinary circumstances occur and perhaps could be referenced in this situation. If you have price escalations included in your contracts those pre-negotiated price increases can be passed onto the owner.
Jeff Scorgie, Partner at Weirfoulds LLP notes, “Parties should carefully examine their contracts to determine whether cost relief is available and be mindful of where to look to determine their entitlement when bidding or negotiating construction contracts. Taking the industry standard form CCDC construction contracts as an example, CCDC 2-2020 Stipulated Price Contract, GC 10.1 provides a potential basis for relief by addressing changes in taxes and duties that occur after the time of bid closing. Cost-plus CCDC contracts, like CCDC 3 and CCDC 5B, treat taxes and duties for which the contractor is liable as a reimbursable ‘Cost of the Work’, which may provide a contractual basis for recovering tariff-related cost increases. However, these provisions only address cost impacts and do not provide for schedule relief. It is also important to recognize that Supplementary Conditions to a CCDC contract may modify these or other clauses in ways that impact entitlement or the process for seeking relief. Contractors should also consider revisiting and updating, if necessary, their subcontract and supply agreement terms and conditions to ensure tariff-related entitlement and exposure are appropriately addressed. Given the strict timelines and procedural requirements in most contracts, proactive contract management and timely engagement with legal and project teams are essential to mitigating tariff-related risks in construction projects.”
Owner Collaboration & Relief Requests:
Regardless of the route taken here, contractors should endeavor to provide prompt and early notice to owners regarding potential impacts. These don’t need to be immediately quantifiable but you should be providing your partners with plenty of time to mitigate and you yourself should be doing whatever is in your power to mitigate cost. Open discussions with project owners are the best way to finding a solution that ensures all parties succeed.
NEW CONTRACTS:
Consider including index-based adjustments in your contracts. These clauses should reference cost indexes of major commodities, such as lumber and steel to adjust the contract pricing as tariffs fluctuate
Where possible, contractors may wish to focus on cost-plus contracts to protect themselves. Of course, this is a smaller portion of the overall construction industry and not all owners will wish to pursue such a contract given the environment.
If there is not enough cost-plus work available for your businesses focus, another mechanism to help insulate against ever changing and unforeseen material costs are larger contingency allowances.
The threat alone of these tariffs has already resulted in a great deal of uncertainty, if things continue along this path, this uncertainty will result in at least some projects experiencing delays. In speaking with Peter Toole, FCA’s VP of Construction Insurance, he noted “Delays caused by damage (Fire, water damage, etc.) to the project may then be compounded by market forces beyond all parties’ control. Delay in start-up insurance protects the project owner against loss of future revenues that are caused by an insured physical loss to the project and ensuing delay. Project owners may not be aware that Delay in Start-up insurance is available to help de-risk their future profits. We’d suggest this key coverage be discussed with your broker and the project owner.”
SUPPLY CHAINS:
Diversification of Suppliers:
Regardless of whether tariffs are applied, contractors should now be focusing on risk proofing their supply chains. Depending on your specific focus, you should be looking at all your critical inputs and be working to cultivate alternative options.
Sourcing material from outside Canada or the US could impact your insurance requirements, so it’s best to speak with your broker to see what changes may be needed to properly protect you and satisfy your contracts.
Inventory Strategies:
Bulk purchasing in advance of when materials may be needed is an option to help avert cost increases on materials that are not yet subject to tariffs but may be impacted in the future, or for materials that are already subject to tariffs which may increase. You will want to discuss these issues with a project owner at the outset, explaining why front-loading materials (and the payment for the same) will ultimately benefit all parties involved.
This is something many contractors and project owners already have experience with due to the global material shortfalls during the height of the COVID-19 pandemic.
Ordering materials in advance likely means you have much more material at risk at the outset of the project than you otherwise would. This will likely result in the need for increased amounts of insurance required at the job site, or in off-site storage
Negotiating with Suppliers:
Andrew Cartwright, Partner and VP Surety at FCA notes, “What you will also need to be careful about is parties looking to take advantage of the situation. Many businesses will be legitimately impacted, others will look to this as an opportunity to increase profits. If a party is telling you there are price increases make sure they quantify this, provide evidence of the price increases, have provided you proper notice and have taken reasonable steps to mitigate cost escalations.”
If you are in an industry where you regularly purchase the same type/quantity of materials on a regular basis, consideration should be given to reviewing and negotiating existing supplier agreements to account for tariff-related cost fluctuations.
Plan Equipment Purchases and Capital Needs:
Tariffs can also impact material capital purchases for contractors. The U.S. market is a significant one for supply of tools and machinery used in construction. If you are considering purchasing equipment in the near future, timing is everything and buying before tariffs take full effect could save money. In addition, with rising costs, demand for used equipment in Canada will likely increase, making it harder and more expensive to find good deals. Contractors with a significant reliance here should make sure they are evaluating these potential impacts and factoring that into their fleet management strategy.
BUDGETS:
In speaking with Sunny Nagra and Nicholas Tomec, Partners at I&A Professional Corporation, they noted the importance of reviewing and adjusting budgets. Any active jobs should have their budgets revised to reflect new pricing. Reduced margins on jobs that rely on imported materials could create cash flow pinches especially when factoring in holdback. These cost changes will also affect over and under billing calculations which could have impacts on revenue recognition. Keeping these reports updated will let contractors know in real time how these costs are impacting project margins so they can take steps necessary to mitigate current and future issues.
Communicate with the Bank and Bonding Company
Sunny and Nicholas also noted how important it will be to ensure you communicate openly and directly with your stakeholders. Every contractor will likely encounter these issues to varying degrees. What is important is that you look forward and determine exactly which of these issues (and others) will have the greatest impact to your business. Open discussions with not just project owners, but also your financial partners whether it be banks, bonding companies, etc. will also be crucial. Those partners will be looking to understand your strategies and how you are proactively insulating your business so they can continue to support you.